Rainier Ave S Bus Lane
አማርኛ • اَلْعَرَبِيَّةُ • 繁体字 • af-Soomaali • Español • Tagalog • ትግርኛ • Tiếng việt • English • 简体中文 • 한국어 • 日本語
December 5, 2024
Improving transit reliability and travel times
What's Happening Now?
Construction of the Rainier Ave S Bus Lane Project began in early September 2024. Crews will work in segments of the project area through spring 2025. We are making these changes to improve the reliability of the Route 7 bus and to prepare for the future RapidRide R Line. Continue visiting our project website or subscribe to our email list for bi-weekly email updates on construction activities.
Over the next two weeks, our crews will continue construction at Rainier Ave S and S Grand St.
Weekday Work
- Crews are currently preparing for signal and light installation on the east side of Rainier Ave S and S Grand St intersection
- Crews will pour sidewalk concrete on the East side of Rainier Ave S at S Grand St on Thursday, December 12
- On Friday, December 13, crews will begin preparing for signal and light installation on the northwest sidewalk corner of Rainier Ave S and S Grand St
- S Grand St at Rainier Ave S will be closed to traffic from Friday, December 13 through Wednesday, December 18
- Bus stop #8460 at S Grand St and Rainier Ave S, servicing the northbound 7 and 106 bus lines, will be temporarily closed through December 20 at 4 PM
Weekend Work
- On Saturday, December 7, crews will saw cut the roadway pavement across the northbound lanes of Rainier Ave S at S Grand St
- On Saturday, December 14, and Sunday, December 15, crews will be digging across Rainier Ave S at S Grand St to prepare for conduit installation. At least one lane will be open in each direction during this work.
Construction Progress
Crews poured concrete sidewalk on east side of Rainier Ave S between S McClellan St and S Bayview St.
What to expect during construction
Typical work hours are Monday - Friday, from 7:00 AM to 4:00 PM. During this time you can expect:
- Temporary traffic revisions to accommodate construction vehicles and equipment
- Temporary parking restrictions near work zones
- Noisy construction activities, such as vehicle backup alarms for safety, heavy truck use, and the use of power tools.
- We anticipate some weekend work during the day on October 12 - 13.
Project Map
Map showing project route and scope for Phase 2 of the Rainier Ave S Bus Lane Project.
Safety improvements at the Rainier Ave S and S Grand St intersection.
Safety improvements at the Rainier Ave S and S College St intersection.
The project’s final design includes:
- New red painted bus lane between S Walden St and S Grand St in the northbound direction
- Sidewalk repair in high transit rider and pedestrian locations on Rainier Ave S
- At S College St and S Grand St:
- New signals to make it easier and safer for people to cross the street
- New marked crosswalks
- ADA-compliant curb ramps
- New streetlights
How did we select Option 1?
In 2022, we did outreach asking you to help us evaluate two options for expanding the bus lane north on Rainier Ave S to S Grand St. Based on your feedback and safety evaluations, we’re moving forward with Option 1 (detailed in the Project Overview section below). Option 1 includes a northbound bus lane from S Walden St to S Grand St, one northbound general travel lane, and keeps the center turn lane.
We selected Option 1 after conducting many different methods of outreach in 12 languages. We ran a digital and paper survey with 1,330 responses, sent a mailer to over 20,000 area residents and businesses, ran digital ads in multicultural media, sent a flyer to families at 14 schools in the project area, and posted updates on social media, the SDOT blog, and our project website. We hosted in-person events at the Rainier Valley Safeway and QFC, Boo Bash and the Big Day of Play. We held a virtual public meeting, and conducted door-to-door outreach with businesses on Rainier Ave S. We partnered with the Department of Neighborhoods and worked with 9 community liaisons to conduct outreach within their own communities and languages (Somali, Tigrinya, Cantonese, Spanish, Tagalog, Vietnamese, Mandarin, Amharic, Korean, and Japanese). Metro helped us hang posters at the 25 most-used bus stops on Rainier Ave S to spread the word about the project and ask for feedback from riders.
We heard a variety of feedback from hundreds of people. We chose Option 1 for several reasons:
- People who walk, bike, or take the bus tended to prefer Option 1
- People preferred Option 1 because they think it will improve safety
- People chose Option 1 to keep a center turn lane for better access to businesses and to reduce crashes from people making turns
- Business owners and the freight community also support Option 1 and keeping a center turn lane to make it easier for freight vehicles to load and unload
- People who drive cars tended to prefer Option 2
- People preferred Option 2 because they think it will help with traffic congestion for car drivers
Regardless of the preferred option, people expressed many similar concerns about increased traffic congestion and safety risks from people speeding or misusing the bus lanes. You can read our complete Survey Analysis and Outreach Summary for more detailed information. Dedicated bus lanes provide a transit option even during times of traffic congestion.
Pilot program to discourage speeding and misuse of the bus lanes
We have heard community concerns about speeding and misuse of the bus lanes. In Winter 2024, we installed raised street markings across the bus-only lane on Rainier Ave S at S Alaska St and additional signs nearby to reinforce appropriate use of the bus-only lane. We are observing traffic and monitoring speeds for up to six months to see if there is a reduction in speeding and misuse of the bus-only lane. We also launched an educational campaign with multicultural media partners in Rainier Valley to help people who are not familiar with bus-only lanes better understand the purpose of bus-only lanes. You can learn more about this effort to discourage speeding and misuse of bus-only lane from our blog post.
Next steps for spring and summer 2024
Project timeline: We’ve finalized the design for this project based on the feedback we received from our community outreach in Phase 2. Now we can start getting ready for construction to begin in summer 2024. We’re also continuing to monitor the pilot program we began this past winter to encourage safe and appropriate use of the bus lanes.
Partnering with King County Metro
We’re partnering with Metro to improve safety, reliability, and access to transit on the Rainier Ave corridor. The Rainier Ave S Bus Lane Project stemmed from feedback from the community engagement that King County Metro led in 2019. This project will improve reliability for the Route 7 in the near term and will support the future RapidRide R Line.
Racial Equity Toolkit
During the design phase, we have included work to develop a Racial Equity Toolkit (RET) for the Rainier Ave S Bus Lane project. This has included internal workshops and sharing a draft with community members for feedback. We’re now working to incorporate and respond to feedback community shared and will be finalizing and sharing the RET via email and on the project webpage.
Responding to community: We’ll be reaching out in person to community members and businesses along Rainier Ave S and sharing construction updates as well as how we’re responding to concerns about speeding and misuse of the bus lanes.
Sign up for email updates to stay informed on the project.
Quick facts about bus lanes
- People driving cars and trucks cannot travel in lanes marked and signed as “bus only”. Lanes painted red are restricted to buses only 24 hours a day and 7 days a week.
- People driving can enter bus lanes to make right turns into driveways and at intersections
- People biking can use bus lanes
- Emergency response vehicles can use bus lanes when responding to an incident
- Only public transportation vehicles are allowed to use marked “bus only” lanes. This does not include school buses, vanpools, work shuttles, motorcycles, carpools or charter buses.
For more information about transit lanes, including bus-only lanes, visit our transit lane webpage.
Project Overview
Bus lanes help keep buses moving more reliably by separating buses from other vehicles. Bus lanes reduce bus travel times, especially when traffic is heavy, by minimizing congestion-related delays. Our goal is to make transit an accessible, convenient, and reliable transportation choice for all people living in, working in, and visiting Seattle. One way we are working toward this goal is by expanding our network of bus lanes to create a more reliable and effective transit system that can move more people in less time.
We're working in partnership with King County Metro to improve transit reliability in the Rainier Valley. Route 7 is one of Seattle's busiest bus routes, serving 8,000 riders per day (11,200 riders per day prior to the pandemic). While Route 7 buses are scheduled to come every 10 minutes or sooner, buses are often delayed due to traffic congestion on Rainier Ave S. To help improve transit reliability on this important corridor, we're adding bus lanes on Rainier Ave S. This work will occur in two phases:
Phase 1 (completed July 2022): We installed a northbound bus lane between S Alaska St and S Walden St, and a southbound bus lane between S Oregon St and S Edmunds St. A travel lane was converted into the new bus lane and no existing on-street parking was removed. We’re monitoring traffic volumes on Rainier Ave S and on other nearby streets to better understand if and how traffic patterns change, we may make future adjustments or implement other changes to help manage and calm traffic.
Phase 2 (construction begins summer 2024):
The goal of this project is to make transit an accessible, convenient, and reliable transportation choice for all people living in, working in, and visiting the Rainier Valley. We’re working toward this goal by expanding our network of bus lanes to create a more reliable and effective transit system.
We’ve spent the past few months reviewing your feedback to better understand how you use Rainier Ave S and how we can make the bus a better transportation option. Based on your feedback we’re moving forward with Option 1 (detailed in the Project Overview section below). Option 1 includes a northbound bus lane from S Grand St to S Walden St, one northbound general travel lane, and keeps the center turn lane. Review our survey analysis summary from January 2023 to learn more about the design differences between Option 1 and 2.
We heard in our engagement about the need for safety of people walking and rolling on Rainier Ave S and maintaining access to businesses. In working to balance the needs of all users, we also considered the needs of the freight community, who require lanes wide enough to move goods safely through the corridor.
Racial Equity Toolkit
Since you last heard from us we’ve been working to develop a Racial Equity Toolkit (RET) for the Rainier Bus Lanes project. This has included internal workshops and sharing a draft with community members for feedback. We’re now working to incorporate and respond to feedback community shared and will be finalizing and sharing the RET via email and on the project webpage.
In 2022 we conducted outreach to hear feedback about proposed changes to further improve transit reliability and travel times, including expanding bus-only lanes further north on Rainier Ave S. During this outreach we shared a survey, staffed pop-up and community events, met with community members and organizations, launched a multicultural media campaign, and hosted a virtual public meeting. To learn more about the this outreach, check our Outreach Summary Report and Survey Analysis Summary.
Option 1, shown below, extends the northbound bus lane on Rainier Ave S to S Grand St. We estimate this change will save people riding the bus 5 minutes during congested morning hours.
Option 1
- Continuous northbound bus lane from S Grand St to S Walden St
- One northbound general travel lane
- Keeps center turn lane
Benefits:
- New traffic signal at S Grand St to promote transit reliability and safer crossings
- Estimated to save nearly 5 minutes of travel time for buses when conditions are more congested than usual
- Makes riding the bus a more reliable and attractive transportation option
- Makes progress toward City climate and equity goals
Considerations:
- Potential for traffic diversion on neighborhood streets
- Travel times for people driving northbound on Rainier Ave S may increase by 9 minutes during the AM peak hours
- May need more investments to address barriers to taking the bus
Image looking north.
Rainier Ave S Bus Lane Map (Phase 1 & 2)
Project Background:
Rainier Ave S is a principal arterial street that connects people to businesses and cultural hubs in the city. It is also a minor freight corridor that connects people moving goods to their destinations. Rainier Ave S is also an important transit corridor serving King County Metro routes 4, 7, 9, 48, 50 and 106.
The Route 7 bus directly serves the growing Rainier Valley and communities that have been traditionally underrepresented and underserved. Many people who live in Rainier Valley depend on the Route 7 bus each day to access local services such as schools, grocery stores, jobs, and community gathering spaces. People continued to rely on the Route 7 during the COVID-19 pandemic and the bus route maintained some of the highest ridership numbers during the pandemic. In fall of 2020, Route 7 retained 60% of pre-COVID ridership.
This project was selected in part as a near-term opportunity to improve bus reliability and travel time on a route where ridership remained high throughout the pandemic. By making these investments now, transit can continue to be a reliable and efficient transportation option for people as we continue to recover from the pandemic.
The Rainier Ave S bus lane project builds from previous outreach and planning efforts to improve transit reliability in Rainier Valley. SDOT and King County Metro conducted outreach in 2017-2018, and again in 2019-2020 to gather community input on transportation needs and priorities along Rainier Ave S as part of the RapidRide R Line project. Through that outreach we heard:
- People want reliable transit to reach destinations and essential services along Rainier Ave S (rather than just to commute to downtown)
- Support for bus trips that take less time and connect to other transit
- Safer access for people walking, biking, and rolling to bus stops (particularly at crossings near bus stops)
- Support for a bus lane between Chinatown-ID and Mt Baker Link Light Rail Station
- Most people support the proposal to remove on-street parking in favor of adding bus lanes, but there are concerns about potential impacts to small businesses
Want to read more about RapidRide outreach? Read our 2019 outreach summary.
Project Benefits
- Adding and expanding bus lanes on Rainier Ave S will improve bus reliability on Rainier Ave S, including frequent routes with high ridership such as the Routes 7, 48 and 106
- Adding bus lanes now will allow transit to continue to be a lifeline and better serve the Rainier Valley community as we collectively recover and rebuild from the pandemic
- Bus lanes will smoothly connect people on the bus to the new Judkins Park Light Rail Station opening in 2023, in addition to existing transit hubs like the Mt. Baker Light Rail Station and the McClellan St Metro Transit Station
- Rainier Ave S provides very frequent bus service in the morning during the AM peak period, with one northbound bus coming about every 3.5 minutes. Bus lanes will help more people get where they are going on-time and experience more consistent travel times. During an average morning trip, people on the bus can save 2 minutes after the bus lane is installed. During the most congested morning trips, people on the bus can save 6 minutes with a bus lane.
- We expect that the Phase 1 project will save over 1 minute for people on the bus traveling north between S Alaska St and S Walden St. We anticipate even more travel time savings for people on the bus by extending the bus lane further north toward I-90 where traffic volumes are higher and congestion is often greater.
Learn more about Rainier Ave S bus-only lanes
We expect that completion of the Phase 1 project will save over 1 minute for people on the bus traveling north between S Alaska St and S Walden St. We anticipate there to be an even greater time savings if the bus-only lane is extended further north toward I-90 where traffic volumes are higher and congestion is often greater. We will continue to evaluate these potential time savings as part of the Phase 2 project.
This project was selected in part as a near-term opportunity to improve transit reliability and travel time on a route where transit ridership remained high throughout the COVID-19 pandemic. Through making these investments now, transit can continue to be a reliable and efficient transportation option for people as we continue to recover from the pandemic.
No existing on-street parking will be removed for the Phase 1 project. Any on-street parking impacts from the Phase 2 project will be determined as project planning and design continue.
No, access to businesses and/or residences on Rainier Ave S will not change with the Phase 1 project. People driving will still be able to enter bus-only lanes to make turns at intersections or into businesses/residences. Any access changes from the Phase 2 project are yet to be determined.
We do not anticipate significant travel time impacts for people driving cars and trucks after the Phase 1 project is built. As part of the Phase 2 project, we will continue to study potential impacts to people driving cars and trucks and work to identify strategies to manage or mitigate those impacts.
We understand that some people driving will choose to take alternative routes through residential neighborhoods to avoid congested streets. Given current traffic volumes, we don't anticipate there to be significant traffic diversion (or people choosing to take alternative routes) from the Phase 1 project.
We know that shifting more trips to transit will be important to:
- help more people benefit from a more reliable transit system, and;
- help lessen the impacts of traffic diversion in local neighborhoods.
We will conduct additional outreach in 2022 as we develop a Phase 2 project to better understand how we can address barriers for people to ride transit. As part of that outreach, we also plan to listen to the local community to better understand:
- concerns and potential strategies we can implement to discourage cut-through traffic
- strategies to help more people shift more trips to transit or travel during less congested times of the day so that the streets can stay clear for when people need to drive.
We've heard that Rainier Ave S is an important street for people biking because it is often the flattest and most direct route. Rainier Ave S is also an important and frequently used route for transit, freight, and other vehicles. We must balance these needs and priorities when making decisions about changes to the street and the limited right-of-way space. To date, we've heard that the community's top two priorities for Rainier Ave S are to reduce crashes and keep buses moving.
People biking are allowed to travel in bus-only lanes in accordance with Washington State law. People biking in curb-side bus lanes should remember that buses will often make in-lane stops and travel with caution. In accordance with State law, whoever is in front has the priority.
While bike lanes are not currently planned for Rainier Ave S, we are making other changes to Rainier Ave S that will improve conditions for people walking, biking, and rolling. Many of these improvements are being constructed with other nearby projects including the Route 7 Transit-Plus Multi-Modal Corridor. The 2014 Bike Master Plan recommends protected bike lanes on Rainier Ave S north of Mt Baker Blvd. As we evaluate options to expand bus only-lanes further north with the Phase 2 project, we will conduct further outreach to understand how people who live, work, and travel on Rainier Ave S use the street now and how people want to use it in the future.
In recent years, we have made other changes to Rainier Ave S to improve conditions and safety on Rainier Ave S, including reducing the speed limit to 25 MPH, installing leading pedestrian signals, and building other safety and traffic calming measures as part of the Rainer Ave Improvements project.
We have made or are making improvements to other nearby routes for people biking, including:
Schedule
- Early 2022: Complete design and begin outreach for Phase 1 project
- July 2022: Construction of Phase 1 project
- Fall 2022: Outreach on Phase 2 project
- 2023-2024: Final design and implementation of Phase 2 project
Phase 1:
Phase 2:
Related Projects
Route 7 Transit-Plus Multimodal Corridor
2019 RapidRide Outreach Summary
Rainier Ave Corridor Improvements
Funding
This project is possible thanks to 80 percent of Seattle voters passing the Seattle Transit Measure (Proposition 1) in November 2020, which created a revenue source for more frequent, reliable, accessible bus service in our city. Through a 0.15% sales tax (the equivalent of 15 cents on a $100 purchase) you are directly supporting access to transit in your community.
Materials
Project materials will be shared here as developed.
- Factsheet (August 2024)
- Outreach summary report (January 2023)
- Survey analysis summary (January 2023)
- Multicultural media campaign report (November 2023)
- Virtual public meeting recording (October 2022)
- Virtual public meeting presentation (October 2022)
- Phase 2 mailer (September 2022)
- Bus stop flyer (September 2022)
- Survey (September 2022)
- Peach Jar flyer (October 2022)
- October 25, 2022 Public Meeting Recording and Presentation
- Factsheet (June 2022)
- Postcard (May 2022)
Translation and interpretation
If you need this information translated, please call (206) 257-2201
如果您需要此信息翻譯成中文 請致電 (206) 257-2201.
Kung kailangan mo ang impormasyon na ito na nakasalin sa Tagalog mangyari lamang na tumawag sa (206) 257-2201.
Si necesita traducir esta información al español, llame al (206) 257-2201.
Odeeffannoon kun akka siif (206) 257-2201.
Nếu quý vị cần thông tin này chuyển ngữ sang tiếng Việt xin gọi (206) 257-2201.
የዚህን መረጃ ትርጉም ከፈለጉ፣ በዚህ ስልክ ቁጥር ይደውሉ: (206) 257-2201.
ናይዚ ሓበሬታ ትርጉም እንተደሊኹም፣ በዚ ቁጽሪ ስልኪ ይድውሉ፡ (206) 257-2201.
당신이 번역이 정보를 필요로하는 경우에, (206) 257-2201 ? 전화 해주십시오.