Project Complete
This project has been completed!
6th Ave Paving Project
Project Overview
Each year, we pave arterial streets in poor condition to make them safer, smoother, and to extend their useful life. Keeping our transportation system in a state of good repair helps lower the cost of future maintenance. Curb ramp upgrades to comply with current Americans with Disabilities Act standards are anticipated to be complete in late April/early May 2018. Grinding and paving between Stewart St and Yesler Way are scheduled to begin in early May 2018. As part of this project, we will also install a new crossing beacon at Marion St.
We selected and prioritized this project based on pavement condition, traffic volumes, opportunities to improve the roadway's operations, and more.
We:
- Upgraded curb ramps and make minor sidewalk fixes at select locations on both sides of 6th Ave
- Repaired the underlying street base
- Grind existing pavement and pave the street curb to curb
- Installed a new crossing beacon to improve safety for people crossing at Marion St
- Replaced traffic detection sensors
Map
Materials
Updated: 5/8/2018