Magnolia Community Center Stabilization
Updated: October 23, 2024
Construction Has Begun!
Seattle Parks and Recreation (SPR) is excited to announce Kassel & Associates, Inc. was awarded the construction contract for the Magnolia Community Center Stabilization Project. The Contractor mobilized and began interior abatement work on June 10, 2024. Community members will see construction fencing erected closely around the Community Center to allow continued sidewalk access. Kassel & Associates has elected to house the job site office within the building to reduce the staging footprint onsite. The construction staging area provides uninterrupted access to the parking lot for Catherine Blaine Elementary teachers, staff, children, and their families. Selective demolition and seismic upgrades began in early July and continued throughout the summer, with window installation and mechanical upgrades to follow.
SPR’s project manager presented to the community in October. View the presentation and learn more about the project and its progress.
Thank you to the Community for your input, advocacy and support during the planning and design stages of this project. We will continue to update you on the progress (with photos!) in coming months.
Community Center Stabilization
Magnolia Community Center was identified in the 2016 Community Center Strategic Plan for a major maintenance project focused on extending the life of the facility and increasing programming potential.
Work includes roof replacement and structural/seismic enhancements for the gym, roof access, fall restraints, structural improvements, window replacement/upgrade for multipurpose rooms, hallway and front entry floor replacement, restroom remodel, accessibility improvements, wheelchair lift between lobby and gym, electrical upgrades, exit signage, ventilation improvements, and kitchen remodel.
Work includes roof replacement and structural/seismic enhancements for the gym, roof access, fall restraints, structural improvements, window replacement/upgrade for multipurpose rooms, hallway and front entry floor replacement, restroom remodel, accessibility improvements, wheelchair lift between lobby and gym, electrical upgrades, exit signage, ventilation improvements, and kitchen remodel.
SPR had a successful bid opening on March 6, 2024, for the Magnolia Community Center Stabilization Project with five bidders. Kassel & Associates, Inc. was awarded the construction contract for the project and was granted a Notice to Proceed (NTP) on June 10, 2024. The facility will be closed for a minimum of a year during construction for the extensive building and accessibility upgrades.
SPR is working closely with Seattle Public Schools, Catherine Blaine Elementary and the Contractor to coordinate the construction schedule and School activities to minimize disruption during the school year.
Schedule
Planning: 2017
Design & Permitting: 2017- 2023
Move our & Pre-Construction Building Prep: October 2023- May 2024
Construction Notice to Proceed: June 10, 2024
Construction: Late Spring 2024 – Fall 2025